New Westminster tree rules for developers and project managers

The detail behind the project tree check: what the City requires at each stage, with the bylaw or guide section for every rule.

How New Westminster's tree bylaw affects development

The same 20 cm limit applies before and during development, but development brings the paperwork: every development application needs an arborist report, and the barrier sign-off gates your demolition and building permits.

What triggers what
ProjectWhat the City needs
Addition, renovation or accessory building near treesSmall Projects stream tree permit. Arborist report if there are 3 or more protected trees, a specimen tree, off-site trees affected or significant digging near roots. Owner-occupiers can have it waived on simple lots.
New house, laneway or carriage house, infill, demolitionDevelopment Projects stream. Arborist report, tree survey, tree protection plan and replacement plan, with building plans, site plan, site service plan and topographical survey.
Rezoning, subdivision, development permit, variance, fill permitArborist report with every application, plus the tree protection and replacement plans. Retained trees carry a security.
Work near trees with nothing removedA CRZ work authorization for any work within 4 m of a protected tree's drip line.

Retention comes first

The City expects arborists to focus on keeping trees and to recommend design changes that make that possible. It can suggest changes to your site plan, and if you accept, your retained tree security is cut by 50% and a variance to fit the redesign is available.

Removal is narrow

A healthy tree can only come out for development if it's in the footprint of something the zoning allows and the plan can't be changed to keep it, as the City decides.

Bylaw 7799, s.5.2.2, s.5.3, s.8.1 and s.9.5; Tree Permitting Application Guides (2025); Arborist Report Requirements, April 2025.

From survey to security refund: the New Westminster tree timeline

The stages most development projects with protected trees go through. The gold stages are gates: nothing moves on site until they're done.

StageGate before permits or site work
  1. Before you apply

    Survey every tree, including the neighbours'

    A BC land surveyor's tree survey of every protected tree on site, and on neighbouring lots and City land within 4 m of the property line, with base elevations and utilities.

  2. Before you apply

    Arborist report, tree protection plan and replacement plan

    Prepared by a TRAQ-qualified arborist with a New Westminster business licence. The City may also ask for a root mapping report along the excavation lines.

  3. Application

    Apply through the Development Projects stream

    With a title search under 72 hours old, consent for any off-site trees, and the $75 application fee.

  4. Review

    City review, usually 4 to 6 weeks

    The City Arborist reviews the reports and plans and returns comments for revision if anything is missing.

  5. Gate

    Barriers built and signed off

    Schedule B barriers around every kept tree, and your arborist's letter with photos approved by the City Arborist.

  6. Gate

    Fees and securities paid, permit issued

    Then paint-mark the trees and post the green placard at least 24 hours before cutting.

  7. Permit

    Demolition, building or fill permit

    Not issued until the barriers have been approved. The tree permit expires 6 months after it's issued.

  8. Construction

    Barriers stay up, arborist supervises

    Any work inside a barrier needs a letter of undertaking and your arborist on site, with a supervision report afterwards.

  9. Replanting

    Plant the replacements

    Within 6 months of the permit unless the City sets another date. 40% of the replacement security comes back on planting.

  10. Afterwards

    Final inspection and security refunds

    Retained tree security after final building inspection; the rest of the replacement security after 12 months.

Bylaw 7799, s.5, s.6.1, s.8.3, s.8.6 and s.9; Tree Permitting Application Guides (2025); UFMS Technical Guidebook (2018), s.2.

New Westminster arborist report and plan requirements

The City's April 2025 requirements and its technical guidebook set out exactly what each document must show. Missing items send the submission back.

DocumentPrepared byWhat it must show
Tree surveyBC land surveyorLocation and DBH of every protected tree on site, and on neighbouring lots and City land within 4 m; base elevations; utilities, easements, building footprints and grades; metric, legible at 11 x 17
Arborist reportISA Certified Arborist with TRAQ and a City or intermunicipal business licenceCredentials, licence and insurance; Level 2 assessment of every tree in a table (species, DBH to 1 cm, condition, risk rating, CRZ, nests); impact assessment and mitigation; reasons for each removal and retention options; photos; signed, valid 12 months
Tree protection planISA Certified Arborist or landscape architectSurveyed trees with tags, separate symbols for kept, moved and removed trees, critical root zones, Schedule B barrier locations and dimensions, utilities, hardscape, grades and access
Tree replacement planArborist or landscape architectNumber, species, caliper and location of replacements, clear of utilities, buildings and existing trees
Root mapping reportISA Certified ArboristWhen the City asks: hand-dug trenches along excavation lines, with each root's position, depth and diameter, photos and a section
Letter of undertakingYour arborist, signed by owner and contractorWhen barriers must move: the works the arborist will supervise, marked on the tree protection plan
Arborist site supervision reportYour arboristAfter each supervision period: dates, works, impacts, mitigation and dated photos
Engineer's reportProfessional engineerIn hazardous conditions development permit areas: slope stability, flooding and erosion

Not sure which of these your project needs? Your free project tree check points you to them, and we can prepare the arborist report, tree protection plan and replacement plan for a fixed fee.

Bylaw 7799, s.2.1(d), (yy), (aaa) and (bbb), s.5.2(m), s.8.6; Arborist Report Requirements, April 2025; UFMS Technical Guidebook (2018), s.2.1 to 2.7; Root Mapping Report handout (2019).

Tree protection barriers (Schedule B)

Barriers go up before any work starts and stay until the City approves their removal. The minimum distance from the trunk is 6 times the trunk diameter.

Trunk diameterMinimum distance from trunk
20 cm1.2 m
30 cm1.8 m
40 cm2.4 m
50 cm3.0 m
60 cm3.6 m
75 cm4.5 m
90 cm5.0 m
100 cm6.0 m

How it's built

50 x 100 mm wood posts with bracing, staked 450 mm into finished grade and no more than 2 m apart, with plastic mesh fixed to a wood frame. A 900 x 450 mm weatherproof Tree Protection Area sign. Set 300 mm back from paving and 600 mm from curbs.

Boulevard trees

See-through fencing at least 0.6 m from the curb and 0.3 m from a sidewalk, leaving pedestrians, hydrants, driveways and crosswalks clear.

Sources differThe bylaw defines the critical root zone as 6 times DBH or 1 m beyond the drip line, whichever is greater, but the Schedule B table uses 6 times DBH only and lists 5.0 m for a 90 cm tree, where 6 times would be 5.4 m. Your arborist sets the final distance on the tree protection plan.
Bylaw 7799, s.2.1(m), s.6.1(c), s.8.4 and Schedule B; Protection for Boulevard Trees handout.

The 4 m rule and CRZ work authorizations

Most construction conflicts come from this rule, and it covers neighbours' and City trees too.

  • The rule. No excavation, demolition, construction, fill or engineering works within 4 m of a protected tree's drip line until a barrier is around its critical root zone and you hold a tree permit that covers it.
  • Nothing being removed? You need a CRZ work authorization instead, with a tree protection plan and your arborist's barrier sign-off. Owner-occupiers can have the City inspect the barrier for a fee. It expires after 6 months, and the yellow placard is posted 24 hours before work.
  • Inside the barrier. No grading, storage of soil or materials, toxic materials, vehicles or heavy equipment, amenity space, or using trunks as winch anchors or power poles.
  • Moving a barrier. Only with your arborist's report on why and for how long, and a signed letter of undertaking that they'll be on site supervising.
Bylaw 7799, s.8.1 to 8.6; Arborist Report Requirements, April 2025.

Tree securities

Two securities, held in cash or a letter of credit from a Canadian financial institution, with no interest paid.

  • Replacement tree security. 40% back when your arborist or landscape architect confirms the planting, and the rest after 12 months of maintenance with their follow-up report. Stakes and wrap must be off and trees in leaf.
  • Retained tree security. For trees kept through a subdivision, development, variance, building, demolition, fill or tree permit, or a CRZ work authorization. Held until final building inspection, then released with your arborist's letter and photos confirming the trees weren't damaged.
  • 50% off for redesign. If the City suggests changes to keep specific trees and you make them, the retained tree security on those trees is halved.
  • Hedges. Every 4 m of hedge counts as one tree for security.
  • Amounts. Set in Schedule E of the Climate Action, Planning & Development Fees and Rates Bylaw No. 7683.
Bylaw 7799, s.5.2.2 and s.9.1 to 9.7; UFMS Technical Guidebook (2018), s.2.8.

Replacement plans on development sites

2 trees for each healthy protected tree removed, 1 for each hazardous or heavily diseased one, and 1 per 4 m of hedge.

Species

From the City's 2025 climate-adapted replacement list, following the 30-20-10 diversity rule. No Japanese maples; dogwoods and magnolias need approval. Drought-tolerant species unless irrigated.

Placement

At least 1 m from property lines and underground utilities, 3 m from dwellings, clear of existing trees and overhead lines. Spacing, stock and planting to the Canadian Landscape Standard.

On City land

For replacement trees on City property, the City picks the species and location, supplies the stock and plants it at the project owner's cost. The owner prepares the soil and tree pit to City standards.

When they won't fit

At least one goes on the lot. If your arborist confirms the rest won't fit, you pay cash-in-lieu at the fee schedule rate.

Bylaw 7799, s.7; Arborist Report Requirements, April 2025; UFMS Technical Guidebook (2018), s.2.5 and s.3; Replacement Trees for a Changing Climate (2025).

What holds New Westminster tree approvals up

Each of these comes straight from the City's rules, and any one can stop a permit.

The wrong arborist

Reports need TRAQ and a New Westminster or intermunicipal business licence, or they aren't accepted.

An old report

Arborist reports older than 12 months aren't accepted.

Missing neighbour trees

Protected trees on neighbouring lots and City land within 4 m belong on the survey and plan.

No barrier sign-off

The arborist's barrier letter with photos must be approved before the tree permit and before demolition, building or fill permits.

A stale title search

It must be from the Land Title Office within 72 hours of applying.

No retention options

Reports that jump to removal without retention options come back for revision.

Construction supervision Any work inside a barrier, or moving one, needs your arborist on site under a letter of undertaking, with a supervision report afterwards. We can quote for it.